What happened in Vancouver
Telus, one of Canada's largest telcos, has pulled out of two AI data centre projects in Vancouver. Daily Hive reported the exit on 14 November. The projects were among the first to move forward under Ottawa's "Enabling large-scale sovereign AI data centres" initiative. Telus and federal AI minister Evan Solomon had announced the partnership on 11 May 2026. At the time, Solomon said "Canada cannot compete in the AI economy without the infrastructure to back it up." The government's own release shows the arrangement rested on non-binding memoranda of understanding, and no federal funding had been committed or paid out.
BetaKit's report from 16 November describes the two sites. One was a 100,000-square-foot repurposed building in Mount Pleasant. The other was a 400,000-square-foot development at 150 West Georgia Street, next to BC Place. BetaKit cites an unnamed source quoted by The Globe and Mail, who said weak local support made Telus reconsider. Hundreds of people protested over the (northern) summer, and both sites were still waiting on rezoning decisions. BetaKit also notes that Telus is carrying heavy debt, is reworking its non-telecom businesses, and has seen its share price fall nearly 25 percent this year. Telus's own statement said only that it had "decided not to proceed" and gave no reason, according to iPhone in Canada.
The scale of the retreat is large. iPhone in Canada reports that the May plan covered three sites with more than 60,000 GPUs and 150 MW of capacity by 2032. Telus is now only committing to grow its Kamloops data centre to 20 MW by the end of 2028, while it looks at other partners and locations in British Columbia. Westbank, the developer, says both Vancouver projects will go ahead with a new Canadian partner that "will meet sovereignty requirements". That partner hasn't been named, and nobody has published what those requirements are.
Why a Canadian telco matters to NZ firms
Canada is a reasonable comparison for New Zealand. Both are mid-sized economies that rely heavily on US hyperscalers, and both governments are under pressure to keep sensitive data and AI processing within national borders. Canada has also committed far more public money than New Zealand. BetaKit notes that Canada's latest federal budget pledged to give Canadian AI companies access to 500 MW of sovereign AI compute. Even with that backing, a flagship telco project lost two of its three sites within six months of being announced.
The forces behind the Telus decision exist on this side of the Tasman too. In Tasmania, Latrobe Council has asked the state government to treat Firmus's proposed Wesley Vale AI data centre as a major project, ABC News reported on 20 November. Firmus is fighting the referral. The ABC notes that major project declarations in Tasmania can take years, while council approvals usually take far less time. In New Zealand, data centre policy was a live election issue. Newswire's summary of party positions records that the Greens called in July for a one-year pause on consenting new AI data centres. NZ First proposed a local storage mandate for personal information held by public agencies, and the Opportunity Party wants all critical New Zealand data hosted onshore. The parties are pushing in opposite directions: some want more data kept onshore, and others want tighter limits on the facilities that would hold it.
New Zealand's onshore AI compute is still thin. OVHcloud's Auckland Local Zone, opened on 5 May 2026, offers compute plus block and object storage, and its launch release doesn't mention GPU or AI services. Some larger organisations have stopped waiting for shared capacity. 2degrees chose to run HPE Private Cloud AI on its own premises, keeping critical data under New Zealand jurisdiction.
What we take from the Telus exit
An announced sovereign AI facility is a statement of intent. The Telus deal had a minister, a named developer and published GPU targets, and two of its sites still fell over on planning opposition and the operator's finances. New Zealand businesses that put "use the local sovereign AI cloud when it opens" into a roadmap or a privacy impact assessment carry that same risk, with less public money behind the projects.
A change of operator matters as much as a cancellation. Westbank says its replacement partner will meet sovereignty requirements, but customers of a sovereign service care about who runs the hardware, who can be compelled to hand over data, and who holds the keys. Those answers can change when an operator changes, even if the building and the location stay the same. Our earlier piece on onshore hosting that still allowed offshore access covered the same weakness from the contract side.
Waiting for large shared facilities isn't the only route to keeping AI workloads private. Many of the AI tasks mid-sized NZ organisations actually run, such as document search, summarising internal records, drafting from templates and triaging tickets, fit on modest hardware running open-weight models. A local AI server sitting in your own rack or a local colocation facility doesn't depend on a rezoning hearing in another city or a telco's balance sheet.
Practical next steps
- Check your AI roadmap and privacy assessments for dependencies on facilities that haven't been built yet. Give each one a fallback that works with capacity you can buy today.
- For any sovereign or onshore AI service you use or plan to use, get in writing who operates the infrastructure, which country's law applies to the operator, and what notice you'll get if the operator or ownership changes.
- Sort your AI use cases by data sensitivity. Workloads involving personal, health, financial or commercially sensitive information are the best candidates for on-premises or locally hosted models, and low-sensitivity work can stay on global services.
- Size a small private AI pilot against one real workload before committing to larger capacity. Measure response times, accuracy and staff uptake on your own data.
- Write exit terms into AI hosting contracts, including how you'll get your data, embeddings and fine-tuned model weights back in a usable format.
- Track the final New Zealand election result and any coalition agreement wording on data centres and local storage, since either could change the hosting options and obligations for public sector clients and their suppliers.
If you're weighing up where your AI workloads should run and who should govern them, our AI consultancy team can help you map sensitivity, hosting options and contract risk before you commit.
Sources
- Telus no longer a partner in Westbank's two Vancouver AI data centre projects (Daily Hive)
- Telus pulls out of two government-backed AI data centres in Vancouver (BetaKit)
- Telus Pulls Out of Vancouver AI Data Centre Projects (iPhone in Canada)
- Government of Canada and TELUS advance work to build sovereign AI infrastructure (Canada.ca)
- Firmus argues proposed AI data centre not major project (ABC News)
- AI policy in New Zealand's 2026 election, party by party (Newswire)
- OVHcloud opens its first Local Zone in Auckland with Datacentre220 (OVHcloud)
- HPE & 2degrees build sovereign AI cloud in New Zealand (IT Brief)
Want to know what this means for your organisation? Our team in Auckland can show you your top three opportunities in a free 30 minute assessment.
Get my free assessment How we help