What a UK savings bank's £840m reset can teach NZ firms splitting up legacy systems

By DataForge team24 November 20265 min read

It'll take National Savings and Investments, the UK's savings bank, another 16 months and an extra £840m to move from a single outsourcer to several. NZ firms planning multi-vendor moves can learn from that.

What happened

The UK government's savings bank, National Savings and Investments, won't finish its business transformation programme without another 16 months and an extra £840m, PublicTechnology reported on 17 November. The revised business case raises the programme's 10-year cost from £2.85bn to £3.84bn. Completion moves from March 2028 to July 2029. Ministers approved the revised case on 5 October 2026, according to the Accounting Officer Assessment published on GOV.UK.

The overrun's drawn so much attention because of how big the bank is. The bank has more than 24 million customers holding over £240bn, according to the National Audit Office. Since 1999 one outsourcer has run its operations, first Siemens and then Atos. The programme formally launched in 2020. The goal was to swap that single contract for five separate ones and move most services across by March 2024. The NAO found in November 2025 that the programme was four years behind schedule. The estimated cost had climbed from £1.7bn to £3bn.

Sir Jim Harra became interim chief executive in March 2026. Harra told MPs in a letter, reported by Civil Service World, that the bank "fundamentally underestimated the complexity of replacing a highly integrated legacy technology and data estate." Harra also said the bank had underestimated the capability needed to manage several suppliers, along with the commercial and technical dependencies between them. The reset replaces the original design with a "simplified solution". The assessment says the new design cuts both technical integration and the work of managing suppliers. HM Treasury has also set up a Sponsor and Oversight Board to make the programme's trade-off decisions.

Why a UK savings bank is relevant to NZ operators

Few NZ organisations will ever run a programme this size, but the same failure happens at much smaller scale. Picture a mid-sized distributor leaving a technology provider it's used for a decade, or a manufacturer retiring an ERP with fifteen years of custom integrations attached. Both face the two problems Harra described. The old system quietly does more than anyone has written down. And once the work is split between vendors, every hand-off between them needs an owner.

The NAO's been unusually specific about where the bank went wrong. The original schedule left no time for testing or contingency, and no time to understand the existing technical infrastructure before replacing it. The auditor said a weak grasp of the system's complexity and interdependencies led to problems in procurement and delivery, and to delays. The bank rated its own programme red in March 2024, which triggered a reset in July 2024. Two more years passed before a credible revised plan was approved.

Look closely at what drove the cost increase. Harra put most of the extra spend down to customer operations costs caused by the delay, plus the cost of keeping legacy systems running. Each month a migration overruns, the organisation pays for the old system and the new project together. The incumbent supplier gains bargaining power too. The Register reported that the savings bank extended Atos's contract without competition, first to 2024 and then to 2028, adding £474.4m to the cost.

Keeping the old system running indefinitely wasn't a safe choice either. The Accounting Officer Assessment says several critical technology components will lose extended support within two to three years. On that basis it concludes that not replacing the core banking capability would raise operational, resilience and service risks. Many NZ firms are in the same position with ageing on-premises ERP versions and unsupported servers. Their vendors' support end dates set the real deadline, whatever the project plan says.

What it means for NZ businesses

The move from one provider to several is common here. A firm might go from a single managed service provider to separate contracts for cloud hosting, the service desk, security and application support. Specialist vendors can offer better value. The risk sits in the joins between them. When an integration fails at 2am, someone has to own the incident from end to end, and someone has to know which supplier's change caused it. When nobody holds that integration role, the business ends up doing it by default, usually without the skills or the time.

The structured practices for this are well established. To keep track of which vendor supports each part and how they coordinate changes, it's worth drawing on the supplier management, relationship management and service configuration management practices in ITIL 4. Those practices need to be running before the second contract is signed. Setting them up after the first cross-vendor outage costs more.

The bank's reset also shows the value of cutting scope. The revised plan came from comparing several options, including a minimum-investment option that only keeps operations going. The simplified solution was preferred because it reduced integration and supplier complexity. NZ firms should treat simplification as a legitimate decision at planning stage. There's no reason to wait until a project's already gone red.

Practical next steps

  • Map the current system's integrations and data flows before going to market. Cover batch jobs, reports staff export to spreadsheets, and the manual workarounds that keep processes running.
  • Estimate what each month of running the old and new environments side by side will cost, and put that figure in the business case.
  • Decide who owns integration between suppliers before signing more than one contract. That owner could be an internal role or a contracted service integrator.
  • Review your incumbent provider's exit and extension terms now: notice periods, extension pricing, and obligations to hand over data and documentation.
  • List the support end dates for every critical component, so the programme timeline reflects the vendor deadlines you actually face.
  • Build contingency into both schedule and budget from the start. The bank's revised business case now has "optimism bias" contingency, which the original plan didn't.
  • Set a formal review point early in delivery where reducing scope or simplifying the target design is an accepted outcome.

The revised plan comes with conditions. The Accounting Officer Assessment calls feasibility "challenging but credible" and makes delivery dependent on funding being secured. The bank hasn't published the revised business case, so the detail of the simplified design isn't public. For NZ organisations planning a supplier split or a core system replacement, the clearest lesson is to spend on discovery and integration ownership early. When you're scoping that work, our digital transformation team can help you plan the sequence before any contracts are signed.