MBIE's second go at border biometrics: rescoping lessons for NZ firms

By DataForge team25 November 20265 min read

MBIE is asking the market about immigration biometrics again after a failed $50m project. Here's what NZ firms restarting a project can use.

The Ministry of Business, Innovation and Employment (MBIE) has gone back to suppliers about immigration identity matching, ten months after ending a project that produced no working system. The new request for information was reported by Biometric Update on 19 November, and RNZ followed with details of the replacement programme on 24 November.

Few NZ companies will ever match fingerprints against 20 million records. Plenty have a half-finished ERP module, customer portal or warehouse system that somebody wants to restart, and MBIE's approach shows what can be settled before a second contract is signed.

What MBIE is asking for

The request covers a Biometric Comparison Capability, and RNZ reports that it isn't a tender. MBIE hasn't finalised its requirements, architecture, procurement route or budget. A business case is due by July 2027, and the cost is still unknown.

Some figures are already public. The system would need to handle peaks of 10,000 face matching requests and 500 fingerprint comparisons an hour against a gallery of 20 million templates, and MBIE says that gallery could grow to 40 million. The same report says MBIE wants information on technical dependencies and avoiding vendor lock-in. Supplier questions are due by 3 December and responses close on 18 December.

The programme behind the request is called Core Identity Modernisation. Immigration deputy secretary Andy Milne told RNZ the new programme replaces the face and fingerprint matching technology and keeps the existing staff interface, a narrower scope than the cancelled project had.

How the earlier project went wrong

The Biometric Capability Update began in 2018 and was suspended in November 2025, then ended in January 2026. Its reported cost has kept moving. June coverage put the figure at about $33m. MBIE later found a further $6m and ordered an independent financial audit. The ministry's estimate is now $42m, plus $8.7m for a linked In Person Enrolment programme.

Greg James's independent review, published in June, found the project started without detailed analysis and was significantly rescoped in 2020 without due diligence. The 2020 change was a move to an off-the-shelf model. The review also found that warnings from assurance reviewers and staff were ignored.

Business owners will recognise the pattern in the budget. B2B News reports that the whole-of-life estimate was revised upward four times between 2019 and 2023, from $19.5m to $35m. The review questioned whether accounting decisions were used to keep the stated cost below the $35m level that would have triggered Cabinet scrutiny. A separate Public Service Commission review isn't complete, so responsibility for those decisions hasn't been settled.

MBIE's annual report adds an accounting lesson. The project was capitalised in June 2025 even though the asset wasn't operational. A finance team that checks whether a system is in use before recording it as a finished asset has a test that doesn't depend on the project manager's status colour.

The damage reached a second programme

The abandoned project was also due to supply an identity capability to Immigration New Zealand's wider rebuild, Our Future Services, so its collapse affected that programme too. The $336m rebuild has a separate benefits problem: its forecast savings of $453m were overstated by $134m, and the programme is on hold.

The source of the overstatement is useful to anyone writing a business case. Officials pointed to residence applications where one officer could process 20 a day, up from five, but that work was simpler and handled by a small team at one site. Milne called the assumed 50 percent productivity gain "pretty much unheard of". The savings estimate also counted about $50,000 of overhead for each role removed, although large shared costs don't disappear when a few jobs go. The same RNZ report says the case had passed an independent quality review and a Treasury review in 2024.

We'd expect the same mistake in many automation proposals. A pilot usually runs on the cleanest transactions with the keenest staff, and the result gets multiplied across branches whose orders are full of exceptions. Passing a review doesn't help much if the reviewers never ask which transactions the productivity figure came from.

What the narrower scope buys

Replacing the matching engine and keeping the screens reduces the amount that has to work on go-live day. Staff don't need retraining on a new interface, and the old and new engines can, in principle, be compared on the same cases. A distributor could apply the same idea by replacing its pricing engine behind existing order screens, leaving the screens for a later budget.

Keeping an old interface has a price. Somebody has to understand how the ageing front end talks to the component being replaced, and that interface will constrain the new component. MBIE hasn't published how the two parts would connect. Integration is where we'd put the early technical effort on any similar project, because an undocumented connection can erase the savings from a smaller scope.

Asking the market before fixing requirements also has limits. Suppliers will describe what they sell, so a buyer needs its own volumes and failure cases in hand. MBIE's published peak loads give suppliers something measurable to answer. Our digital transformation guide covers readiness and roadmap work, and the process and automation page is the better starting point if the workflow itself is in doubt.

What to do before you restart a project

  • Write a one-page account of the previous attempt. Include the original budget, every approved change and all related costs, including staff time and linked projects. Have finance sign off the total.
  • Treat a change of approach as a new project. Moving from custom build to packaged software, or the reverse, should need a fresh business case and a fresh decision to proceed.
  • Set approval limits on whole-of-life cost. Count split phases and transferred costs together, so that a project can't slip under the limit by being divided.
  • Give warnings a route past the project team. Send independent reviews and staff concerns directly to the sponsor or board, and record the response to each one.
  • Test benefits on your hardest work. Measure the pilot on messy transactions as well as simple ones, then claim only overhead that finance agrees will leave the accounts.
  • List what depends on the project. For each dependent system, agree a fallback and a date on which you'll switch to the fallback.
  • Publish numbers to suppliers before features. Give them peak volumes, expected growth and acceptable error rates, then ask how you'd get your data out at exit.

If you can complete that list in a fortnight, you'll know whether the second attempt deserves funding. If the cost total or the dependency list can't be completed, the project isn't ready for a supplier conversation.