DIA's $23m registry restart rated amber-red: lessons for NZ firms

By DataForge team28 November 20264 min read

Internal Affairs' second attempt to replace its births, deaths and marriages system is stalled at the business case. Here's what NZ firms can learn.

What happened at Internal Affairs

On 26 November, RNZ's Phil Pennington reported that the Department of Internal Affairs' restarted replacement of the births, deaths and marriages register, now called Civil Registration 2.0, is still at the preliminary planning stage and has no completion date. The register holds about 80 million records on 25-year-old technology, and DIA spent $30 million last year keeping the existing system stable.

The restart follows an expensive false start. DIA announced the replacement in August 2022, ended its contract with Australian supplier DWS in late 2023 and abandoned the project in 2024. According to RNZ's June 2025 report, the department wrote off $22.9 million, returned an unspent $58 million to the Crown and is still in dispute with DWS. Cabinet approved a fresh attempt in 2025.

A Treasury-ordered Gateway review in January 2026 found the new business case at an early stage, put low confidence in the cost estimate and rated delivery amber-red. The reviewers wrote that "the current plan is deemed overly aggressive, high-risk, and reliant on excessive parallel activities." They made eight urgent recommendations, and three have been reported: rework the financial case, bring in the government chief digital officer to avoid rework or unforeseen costs, and strengthen the case for change. A follow-up review planned for November hasn't taken place. DIA's chief financial officer told RNZ that Treasury would publish an update on scope, cost and timeline soon. No date has been given.

Why a registry is hard to replace

The difficulty sits mostly outside the core database. Many other agencies draw information from the register, and RNZ describes the current system as a patchwork of disparate technologies. Each agency that reads from the register is an interface the replacement has to support from the day it goes live, and each one brings its own testing, data formats and change approvals.

The second difficulty is people. RNZ reports that Civil Registration 2.0 may have to wait until DIA's $300 million Te Ara Manaaki programme finishes, so the registry project can draw on Te Ara Manaaki's experienced staff. In August, DIA said the scope of the new system had not yet been determined and described the old platform as stable "although increasingly expensive to modify". With the scope still open and the senior delivery staff committed to another programme, the timeline can't firm up, and every year of delay adds to the $30 million maintenance bill.

The reviewers also found the team had tried to learn from the failed first attempt and hadn't gone far enough. We think that finding deserves the most attention from private-sector leaders. A restarted project is normally run by many of the same people, inside the same governance, under pressure to show progress quickly. Unless the reasons for the earlier failure are written down and fixed, the second plan tends to repeat the first plan's assumptions with a shorter timeline.

The wider pattern in the public sector

DIA's registry project has company. A DIA paper from September 2025 found 59% of core government digital projects behind schedule and 85% rated high risk for size and complexity, within a $13 billion five-year investment pipeline. Public Service Commissioner Sir Brian Roche's rapid review in July 2026 pointed to weak prioritisation and an approval process designed around large capital programmes. The same RNZ report notes MBIE wrote off $50 million on a biometrics project this year.

What it means for NZ businesses

Most NZ firms don't run 80 million records, but plenty run a core system that has quietly become the source of truth for everything else: an old ERP, a custom job-management database or a policy administration platform. The registry's problems scale down well. When finance, payroll, the website, the warehouse and a few spreadsheets all read from one system, replacing that system means replacing every feed as well as the system itself, and the feeds are usually where the cost estimate goes wrong.

The maintenance bill matters as well. DIA's $30 million in a single year shows the cost of a "stable" legacy platform. A business case that leaves the run cost of the old system out of the comparison will overstate the risk of moving and understate the risk of staying put. In mid-sized firms the parallel-activity warning applies with more force. Data cleansing, testing, training and the normal month-end close often fall to the same handful of people, and a plan that schedules all four at once will slip.

DIA's 2025 statement that earlier work on design, data quality, data migration and testing may be reused is a useful reminder. Data cleansing and test cases often survive a failed project intact, so a write-off rarely means every piece of work was wasted.

Practical next steps

  • List every system, report and spreadsheet that reads from your core platform, with an owner for each feed. Treat the list as the real scope of any replacement.
  • Put the full annual cost of keeping the current system running, including workarounds and staff time, next to the replacement estimate in the business case.
  • If you're restarting a failed or paused project, write a short post-mortem before you redraw the plan, and have someone outside the original team test the new plan against the post-mortem.
  • Count the named people each workstream needs. Where data migration, testing and business-as-usual depend on the same staff, put the workstreams in sequence or bring in backfill.
  • Schedule an independent review at the business-case stage, before contracts are signed, and agree in advance what result would stop the project.
  • Keep the deliverables from earlier attempts, especially data mapping, cleansing rules and test scripts, in a place the next team can find them.

Our digital transformation guide covers how we structure staged replacements. Firms facing an ageing finance or operations platform can read about our ERP work before they scope a business case.